<Project Name>
Work Orders (dd/mm/yy to dd/mm/yy)
Version <1.0>
[Note: The following template is provided for use with the
Unified Process for EDUcation. Text enclosed in square brackets and displayed
in blue italics (style=InfoBlue) is included to provide guidance to the author
and should be deleted before publishing the document. A paragraph entered
following this style will automatically be set to normal (style=Body Text).]
[To customize automatic fields in Microsoft Word (which
display a gray background when selected), select File>Properties and replace
the Title, Subject and Company fields with the appropriate information for this
document. After closing the dialog, automatic fields may be updated throughout
the document by selecting Edit>Select All (or Ctrl-A) and pressing F9, or
simply click on the field and press F9. This must be done separately for
Headers and Footers. Alt-F9 will toggle between displaying the field names and
the field contents. See Word help for more information on working with fields.]
Revision History
|
Date |
Version |
Description |
Author |
|
<dd/mmm/yy> |
<x.x> |
<details> |
<name> |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Table of Contents
1.3 Definitions, Acronyms, and Abbreviations
3. Work Orders Reports and
Schedule
Work Orders (dd/mm/yy
to dd/mm/yy)
[The introduction of
the Work Order provides an overview of the entire document. It includes
the purpose, scope, definitions, acronyms, abbreviations, references, and
overview of this Work Order.]
[Specify the purpose
of this Work Order.]
[A brief description
of the scope of this Work Order; what model it is associated with and
anything else that is affected or influenced by this document.]
[This subsection
provides the definitions of all terms, acronyms, and abbreviations required to
properly interpret the Work Order. This information may be
provided by reference to the project's Glossary.]
[This subsection
provides a complete list of all documents referenced elsewhere in the Work
Order. Identify each document by title, report number if applicable,
date, and publishing organization. Specify the sources from which the
references can be obtained. This information may be provided by reference to an
appendix or to another document.]
[This subsection
describes what the rest of the Work Order contains and explains how the
document is organized.]
[State the week of work:
Week number and dates (dd/mm/yy to dd/mm/yy) to which these work orders
apply]
[Explain briefly the naming convention for the work orders
ID. Example:
All work orders ID use the following convention:
<RR-IT#-W##-##> where:
RR: Resource
(Work Order Holder) initials
IT#: Related Iteration Number
W##: Week
of work Number
##: Unique work order number
On week of work #1, John Smith has been assigned his 1st
work order. It is related to Iteration
#1. Work Order ID would be: <JS-IT1-W01-01>]
[State the name of the related iteration to which these work
orders apply]
[Briefly describe the main objectives of this iteration. Then refer to the Iteration Plan Document for
detailed information]
[List all team members and their role. List only team members implied in this Work
Orders Document]
[State the responsible for this document (Project Manager,
Configuration Manager...)
|
Work Order for <Project Name> |
Created on: <6/6/2002> |
|||
|
Identification |
||||
|
WBS ID: <> |
||||
|
|
||||
|
Responsibility (Holder) |
||||
|
|
||||
|
|
||||
|
Associated Change Reports |
||||
|
|
||||
|
|
||||
|
Schedule |
||||
|
Start: <dd/mm/yy> |
Completion: <dd/mm/yy> |
Critical Path: <dd/mm/yy> |
||
|
|
||||
|
Efforts and Other
Resources |
||||
|
Staff Hours: |
Other Resources: |
|||
|
|
||||
|
Description |
||||
|
Work Description: |
||||
|
Expected Output(s): |
||||
|
|
||||
|
Signature Agreement |
||||
|
Project Manager: x _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
_ _ _ _ Signed on: <dd/mm/yy> |
Work Order Holder: x _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
_ _ _ Signed on: <dd/mm/yy> |
|||
[The following is a brief outline on the work order report]
1. Identification
Uniquely identifies the work order and identifies the work
package (Work Breakdown Structure (WBS) identification)
associated with this work order: effort expended on this work order will be
allocated to this work package for tracking.
2. Responsibility
Organizational positions responsible for fulfilling the work
order.
3. Associated Change Requests
If any, references to Change Requests that are associated
with this work order (those that were the stimulus for it or those that will be
fixed coincidentally).
4. Schedule
The schedule covers the estimated start and completion dates,
and the critical path completion date.
5. Effort and other resources
Addresses the staff-hours, total and over time, as well as
other resource budgets; for example, development environment time, test
environment time.
6. Description of work and expected outputs
Describes what is to be done and what is to be
produced—references the Unified Process for EDUcation description of the
activities to be performed and artifacts to be produced, or the development
case, as appropriate.
7. Indication of agreement between Project Manager
and responsible staff
The work order should be signed and dated by the holder of
the responsible position (usually a team lead) and the Project Manager.