Overview >
Lifecycle >
Inception >
Milestone
|
|
Essential Artifacts (in order of importance) |
State at milestone |
| Vision | The project's core requirements, key features, and main constraints are documented. |
| Risk List | Initial project risks identified. |
| Iteration Plan | Iteration plan for first Elaboration iteration completed and reviewed. |
| Glossary | Important terms defined; glossary reviewed. |
| Use-Case Model (Actors, Use Cases) | Important actors and use cases identified and flows of events outlined for only the most critical use cases. |
| Project Repository, Change Request | The Configuration Management environment should be set up. |